Numerical aptitude · Time and motion

Time and work, made easy

💡 The idea

Turn days into work per day. If Ali paints a wall in 4 days, he paints ¼ of the wall each day.

Ali ¼ a dayBen ⅙ a dayleft
Together they paint ¼ + ⅙ = 5/12 of the wall each day

🧭 The method: 3 steps

  1. Write each person’s work per day: 1 ÷ days.
  2. Working together? Add them. Something undoing the work? Take it away.
  3. Time for the whole job = 1 ÷ (work per day).

🎬 Every kind of question, in pictures

Pick a kind. Guess the answer first, then watch the picture work it out. Tap any step to see it in the picture.

Loading the pictures…

✏️ Worked examples

Example 1. Ali paints a wall in 4 days, Ben in 6 days. Together?

  1. Ali: ¼ a day. Ben: ⅙ a day.
  2. Together: ¼ + ⅙. Same bottom (12): 3/12 + 2/12 = 5/12 a day
  3. Whole wall (12/12) ÷ 5/12 = 12 ÷ 5 = 2.4 days

⚡ Shortcut: (4 × 6) ÷ (4 + 6) = 24 ÷ 10 = 2.4 days.

Example 2. Together they finish in 6 days. Ali alone takes 10. Ben alone?

  1. Together per day: 1/6. Ali: 1/10.
  2. Ben = 1/6 − 1/10 = 5/30 − 3/30 = 2/30 = 1/15
  3. Ben alone takes 15 days

⚡ Shortcut: (10 × 6) ÷ (10 − 6) = 60 ÷ 4 = 15.

Example 3. 6 workers build a wall in 10 days. How long for 4 workers?

  1. Total work = 6 × 10 = 60 worker-days
  2. 4 workers: 60 ÷ 4 = 15 days

⚠️ Where people go wrong

  • Never add the days (4 + 6 = 10 days is wrong): together they must be faster than either alone.
  • More workers → fewer days (multiply and divide the opposite way).
  • “p% more efficient” means divide the time by (1 + p/100), not take p% off.

📌 Remember

  • Work per day = 1 ÷ days
  • Two together = (a × b) ÷ (a + b)
  • Workers × days = total work

🎯 Now you try

Fresh questions every time, with the full solution. Pick a level and go.

Loading questions…

⏱️ Take a 10-question timed test on time and work